US Grid [1/3] America's Transformer Shortage: Why the US Grid Can't Keep Up With AI Data Centers

America's Transformer Shortage: Why the US Grid Can't Keep Up With AI Data Centers (Part 1 of 3)

Part 1 of 3 in a series on the US grid build-out and the Korean companies supplying it. Figures as of late October 2026; won amounts converted at about ₩1,330 per dollar.

If you want a large power transformer for a new substation in the United States, the honest answer from most factories today is: maybe in 2029. That single fact explains a lot about the stock market in 2026. It explains why GE Vernova's grid business keeps raising guidance, why utilities are paying deposits years in advance, and why a group of Korean manufacturers became some of the best-performing industrial stocks in Asia before giving much of it back this year.

This first post looks at the demand side: who is buying grid equipment, how big the gap is, and whether the latest round of Big Tech earnings changes the picture.

Key takeaways

  • US investor-owned utilities expect to spend about $239 billion on capital projects in 2026, up 17% in a year, and about $1.4 trillion from 2026 to 2030.
  • Lead times for large power transformers are around 128 weeks; generator step-up units passed 160 weeks in early 2026. Prices are up roughly 77% since 2019.
  • Big Tech's 2026 capex still adds up to roughly $700 billion, but Alphabet and Microsoft held off raising their numbers in October. That matters more for switchgear than for big transformers.

About this series

Part 1: America's transformer shortage and the AI power crunch (this post)

Part 2: Korea's grid equipment makers vs GE Vernova, Siemens and Hitachi

Part 3: Peak or plateau? Risks, scenarios and a stock scorecard

Read all parts of the series

Two engines of demand

It is tempting to frame the whole story as "AI needs power." That is only half of it. Most of the transformers being ordered today are for utilities, not data centers. J.P. Morgan estimates that 80% to 90% of Korean suppliers' backlogs come from utilities and grid operators rather than data-center developers.

Engine 1: utility capital spending

The Edison Electric Institute, which represents investor-owned utilities, expects member capex of about $238.8 billion in 2026, up from a record $204.1 billion in 2025. Much of that money goes to replacing aging equipment, hardening the grid against storms and wildfires, and connecting new generation. Because utility spending is approved by regulators and recovered through rates, it tends to be steadier than tech spending.

US investor-owned utility capital expenditure 2025 vs 2026
Utility capex has set records for more than a decade, and 2026 is another big step up.

Engine 2: data centers and Big Tech

The second engine is the one that grabs headlines. Amazon, Alphabet, Microsoft and Meta together are on track to spend roughly $700 billion on capital projects in 2026, much of it on AI data centers. Each new campus needs substations, transformers and switchgear before a single server is switched on.

2026 capital expenditure guidance for Amazon, Alphabet, Microsoft and Meta
Approximate 2026 capex guidance. Fiscal years differ, so treat these as ballpark figures.

The October earnings season added a note of caution. Alphabet's third-quarter capex of about $51 billion came in below forecasts, and it kept its 2026 range unchanged while promising a "significant increase" in 2027. CNBC reported that both Alphabet and Microsoft held off raising their capex forecasts. Meta, meanwhile, guided to $135–145 billion and reported negative free cash flow, which the market did not like. None of this is a collapse in spending, but it is the first sign that the pace of increases may slow.

What the power data says

The US Energy Information Administration expects electricity consumption to hit back-to-back records: about 4.29 trillion kWh in 2026 and 4.36 trillion kWh in 2027. For the first time on record, commercial-sector use, which includes data centers, is expected to exceed residential use.

US electricity consumption forecast 2025 to 2027 EIA
After two decades of flat demand, US electricity use is growing again.

Forecasts of how much of this comes from data centers vary widely. Grid Strategies sees US peak demand rising by 128 GW over five years but argues utility projections of about 90 GW of new data-center load by 2030 are inflated, closer to 65 GW in its view. BloombergNEF projects US data-center demand rising from about 25 GW in 2024 to 106 GW by 2035. The spread tells you that not every announced data center will be built.

The bottleneck: transformers and breakers

The US imports roughly 80% of its large power transformers. Domestic capacity shrank for decades, and the equipment is hard to scale quickly: the largest units are custom-built, weigh hundreds of tons, and require specialized steel and testing.

US power transformer, generator step-up transformer and circuit breaker lead times in weeks
Average lead times, per Wood Mackenzie surveys.

Wood Mackenzie estimates that demand for generator step-up transformers rose 274% between 2019 and 2025, and demand for substation power transformers 116%. With supply unable to keep up, prices followed. Wood Mackenzie also put the 2025 supply shortfall at about 30% for power transformers and 10% for distribution transformers.

Transformer demand growth and price increase since 2019
Demand has more than doubled while prices are up by roughly half to three-quarters.

Utilities have adapted. They are ordering equipment years ahead, refurbishing old units, standardizing designs and, increasingly, asking large customers such as data-center developers to prepay for long-lead gear. Some developers now choose sites based on where a substation can be energized soonest.

The 765 kV build-out

The next wave is at the very top of the voltage ladder. Texas, the mid-Atlantic and the Midwest are planning 765-kilovolt backbone lines, the highest transmission voltage used in the US. These need extra-high-voltage transformers and reactors that only a handful of factories in the world can build.

ProjectRegionEstimated costStatus
ERCOT Eastern Backbone 765 kVTexas$9.4 billionApproved by ERCOT board
Permian Basin 765 kV planTexas~$9 billion + ~$5 billion local upgradesApproved April 2025
Valley Link 765 kVPJM (Mid-Atlantic)~$6 billionApproved
MISO long-range tranche 2Midwest$1.2 billion segmentDevelopers selected

Most of this equipment will be delivered between 2027 and 2030, so it supports order books well beyond the current data-center cycle.

Tariffs: a moving target

Trade policy adds another layer. Since April 6, 2026, the US Section 232 regime taxes imported grid equipment on its full customs value. Large power transformers get a temporary 15% rate through the end of 2027, while distribution transformers and cables pay 25%. A "snapback" clause lets Washington raise the rate if imports from one country surge. Korean brokers estimate suppliers are passing about 80% of the tariff cost on to customers, which only works while buyers have no alternative.

What the market leaders are saying

GE Vernova, the largest US-listed grid supplier, reported third-quarter Electrification orders of $5.4 billion with a book-to-bill ratio of about 1.4 and cited "continued strong demand for grid equipment particularly in North America." Its Electrification equipment backlog reached $42.2 billion, up 60% from a year earlier, and it announced a $9 billion deal to buy high-voltage equipment maker Trench Group, partly to add capacity for US 765 kV work. When the biggest player is spending $9 billion to buy capacity, it suggests the shortage is not over.

FAQ

Why can't US factories just build more transformers?

They are trying. Hitachi Energy, Siemens Energy and Korean makers are all expanding US plants, but large units need specialized equipment, trained workers and long qualification periods. Most new capacity arrives in 2027–2028.

Does slower AI spending end the shortage?

Not immediately. Utility spending is the bigger share of transformer demand. Slower data-center growth would hit switchgear and smaller transformers first.

Sources: Edison Electric Institute; US EIA Short-Term Energy Outlook (Oct 2026); Wood Mackenzie via pv magazine and Reuters; Grid Strategies and BloombergNEF via Utility Dive; CNBC (Oct 28–29, 2026); S&P Global; GE Vernova Q3 2026 earnings release (Oct 28, 2026); RTO Insider; SK Securities. Independent research for information only; not investment advice.

Comments

Popular posts from this blog

Intel [3/3] Is Intel Stock Cheap After the Crash? Valuation, Price Targets and a Scorecard

US Grid [2/3] HD Hyundai Electric, Hyosung Heavy, LS Electric: Korea's Grid Equipment Makers vs GE Vernova, Siemens Energy and Hitachi

Robot Drivetrain [5/5] HIGEN RNM, Woorim PTS and a Seven-Company Comparison of Korea's Robot Drivetrain Names